Public procurement: the mandatory standstill period

Those involved in public tenders will be familiar with the requirement that a mandatory ten day “standstill period” must follow all contract awards, during which the contracting authority is not allowed to enter into a contract with the successful bidder.

The purpose of the standstill period is to enable unsuccessful bidders to review and digest the award notification letter and any other debrief materials provided by the contracting authority, and determine whether they have any grounds on which to challenge the outcome of the tender.

If an unsuccessful bidder issues court proceedings within the ten day standstill period, an automatic suspension comes into place which prevents the contracting authority from entering into the contract until the claim is concluded or the earlier lifting of the suspension by the Court.

However, the Public Contracts Regulations 2015 provide that there is an overall limitation period for procurement challenges of 30 days, which runs from the date on which the unsuccessful bidder knew there had been a breach of the Regulations.

In the recent Court of Appeal case of Energy Solutions EU Ltd v Nuclear Decommissioning Authority (which was in fact brought under the now-superseded Public Contracts Regulations 2006, but the provisions relating to standstill and limitation are the same in both sets of Regulations), the NDA sought to argue that a bidder whose challenge was brought within the 30 day limitation period provided for by the Regulations, but after the expiry of the ten day standstill period, should not be permitted to recover damages.

The crux of NDA’s position was that if bidders do not issue proceedings within the standstill period, but wait until after the contracting authority has entered into the contract, they put the contracting authority at risk of having to pay both the successful bidder for performing the contract, and damages to the unsuccessful bidder if the claim is successful.  Unsuccessful bidders should, NDA said, be obliged to mitigate their losses by issuing proceedings within the standstill period, so as to ensure that the automatic suspension comes into place.

However, the Public Contracts Regulations 2015 provide that there is an overall limitation period for procurement challenges of 30 days, which runs from the date on which the unsuccessful bidder knew there had been a breach of the Regulations.

The Court did not accept NDA’s arguments. The High Court judge who initially heard NDA’s application stated that it is “an inevitable consequence that authorities who do not comply with the rules are at risk of being penalised … for better or worse this is now a feature of the procurement law landscape.

The Court of Appeal agreed, noting that there is nothing in the Regulations to suggest that a bidder should be deprived of damages simply because they have failed to invoke a potential remedy.  Taking advantage of the automatic suspension is an option for unsuccessful bidders, but it is not mandatory and is not a pre-condition to the availability of damages.

Given that the Regulations already impose a very short deadline of 30 days for bringing legal action, it is good news for bidders (who may not always wish to prevent the contract from being concluded with another bidder, if they are satisfied with the remedy of damages) that NDA’s attempt to shorten it even further was not upheld.

Nonetheless, an unsuccessful bidder who suspects that the public authority may not have followed proper processes should always take urgent legal advice before the standstill period expires to ensure that its position is protected.  Meanwhile, contracting authorities who are concerned about the financial risk of damages claims brought after the expiry of the standstill period may wish to consider delaying entering into the contract until the 30 day limitation period has also expired.

Disclaimer

This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 14 April 2026
  • Employment

Updates to Vento Bands 2026: Injury to feelings awards

For discrimination and detriment cases, compensation can also cover non-financial losses, which, in most cases, will include an injury to feelings award.

art
  • 13 April 2026
  • Litigation and dispute resolution

Renters’ Rights Act coming into force on 1 May 2026

The long-awaited Renters’ Rights Act 2025 (RRA) comes into force on 1 May 2026, bringing the biggest changes to the private rental sector since the 1980s. So what do landlords need to know about what is changing?

art
  • 13 April 2026
  • Immigration

Sponsor Licence Compliance in 2026: Increased Scrutiny, Increased Risk – Time to Audit

The Home Office’s latest updates to sponsor guidance in March 2026, alongside broader immigration rule changes introduced this year, signal a decisive shift in the UK’s sponsorship regime.

art
  • 10 April 2026
  • Privacy and Data Protection

Is your tech discriminatory?

Employers are increasingly reliant on technology to assist with all kinds of functions – from strengthening security to streamlining recruitment processes.

art
  • 09 April 2026
  • Employment

Bereaved Partner’s Paternity Leave: the new statutory right explained

The new statutory right is not inconsequential, and so to ensure that everyone is up to date: here is what you need to know about this new right.

art
  • 02 April 2026
  • Commercial Real Estate

Can I have access to a neighbour’s land to carry out works to my property?

As a landowner, maintaining and repairing your property is important. It may be the case that to do so, you will need to access the land of a neighbour.