Search

How can we help?

Icon

Payment in Construction Contracts – What’s new?

Payment provisions are an industry “hot topic” and the wave of litigation since the 2009 amendments to the Construction Act remains relevant.

While the position has stabilised somewhat, payment disputes continue to plague the courts. In this article, we take a look at some more recent cases and the guidance offered to assist in navigating the payment mine field.

Balfour Beatty v Grove Developments [2016] – losing your entitlement to interim payment

In this case, the parties agreed that stage payments would apply to their JCT Design and Build 2011 contract, but included only 23 payment dates in their payment schedule. As works were in delay, there was a dispute over entitlement to future payments once that schedule had expired. When Balfour Beatty attempted to make a 24th application, Grove argued that the contract gave them no entitlement to do so, and the Technology and Construction Court agreed.  It was appealed to the Court of Appeal which ruled that:

  • the contract plainly allowed for 23 interim payments, which was adequate provision as required by the Construction Act;
  • there was no reason to imply a term into the contract allowing for further interim applications beyond these 23; and
  • the Court would not rescue Balfour Beatty from what was perceived as a “bad bargain”.

Had the contract stated that interim payments would be at monthly intervals (as opposed to 23 distinct monthly intervals), or made clear what would happen beyond the 23rd application date, this problem would likely never have arisen

Kilker Projects Ltd v Rob Purton [2016] – challenging a final account after adjudication

Kilker was ordered following an adjudication to pay the full £147,223 claimed in Purton’s final account, having failed to issue a payment or pay less notice, but commenced a second adjudication for assessment of the true value of works. Kilker was successful and Purton was ordered to repay almost £67,000, but refused on grounds that the first adjudicator had decided how much he was entitled to and the second adjudicator had no jurisdiction to determine this amount again.

As in the Court of Appeal in Harding v Paice (2014), the court disagreed and ruled that:

  • the second adjudicator did have jurisdiction and the decision should be enforced;
  • notice provisions were intended to encourage cash flow, not to finally determine the value of the contract; and
  • a party could challenge the value of a final account after being ordered to pay the full amount, but not of an interim application.

A party who fails to issue a notice in respect of an interim application will not be able to rectify any overpayment until the next application is made.

Kersfield v Bray [2017] – you still can’t reopen an interim application

A dispute arose between the parties over an interim payment and Kersfield’s failure to serve a valid payment or pay less notice.  An adjudicator awarded that Bray should be paid the full amount of their interim application, but in subsequent enforcement proceedings. Kersfield argued that:

  • Bray’s application was invalid as two claimed items were not sufficiently substantiated;
  • the notice was issued inside the Construction Act timeframes, which could not be contracted out of and therefore must apply; and
  • it was entitled to commence a second adjudication to assess the true value of Bray’s interim application.

The court stressed that while failure to substantiate might warrant rejection of a claim, it did not in invalidate the application.

The second adjudicator did have jurisdiction and the decision should be enforced

The court also disagreed with Kersfield’s second argument, noting that the Act was not concerned with methods and deemed date of service, which the parties were free to agree between them. Nothing in the Act would restrict the terms of the contract in this regard.

Kersfield’s final argument was an interesting one. The Scheme provides that an adjudicator may “open up, revise and review” any non-final decision or certificate, and Kersfield believed this should include Bray’s application (as default payment notice). They also suggested that section 111(8) of the Construction Act permitted an adjudicator to reopen and consider the true value of an application. The court disagreed, ruling that Bray’s notice was not a decision or certificate for the purposes of the Scheme, and section 111(8) did not permit revision of a notice, rather the award of additional sums by an adjudicator. In any event, it only applied when a valid notice had been issued.

Summary

The outcome of the cases above is not especially surprising and serves only as a stark reminder of the consequences of failing to issue notices on time or at all.

If you would like some practical guidance on how to avoid falling foul of payment provisions, contact our construction team.

About this article

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

About this article

Read, listen and watch our latest insights

art
  • 09 December 2024
  • Corporate and M&A

UK Directors’ Responsibilities

On becoming a director of a company, directors undertake to comply with various duties and responsibilities. which are specified in the Companies Act 2006. In this article, we will explain how you can comply with these practical responsibilities.

art
  • 09 December 2024
  • Commercial Real Estate

What happens to a sublease when the headlease is surrendered, forfeited or disclaimed?

The intermediate tenant under the headlease falls away and the tenant under the sublease becomes the direct tenant of the superior landlord.

art
  • 09 December 2024
  • Employment

Mistletoe and Missteps: Preventing Harassment at Christmas Parties

As the festive season approaches, offices are coming together for their annual Christmas parties, offering a chance to unwind and celebrate the year’s achievements. However, whilst these events provide a necessary release and recognition of employee’s contributions, they also present a heightened risk of inappropriate behaviour, particularly sexual harassment.

art
  • 03 December 2024
  • Immigration

UPDATE – Ministers to postpone full eVisa rollout amid fears of UK residents being stranded abroad

The UK government will postpone the full transition to eVisas, initially planned for 1 January 2025, following concerns that system glitches could leave UK residents stranded abroad.

art
  • 02 December 2024
  • Litigation and dispute resolution

The Era of AI

In this recent case, the First-Tier Tribunal gave a stark warning to litigants about use of AI in litigation.

art
  • 28 November 2024
  • Employment

Employment Rights Bill: The Regulatory Policy Committee opinion

This article considers the Regulatory Policy Committee’s recently published opinion on the impact assessments for the Employment Rights Bill. The Committee assessed the quality of evidence and analysis used to inform the government proposals and came to the overall opinion that the impact assessments are currently “not fit for purpose”.