Search

How can we help?

Icon

Claims for payment – when is it too late?

One of the first things you learn as a law student is that the standard limitation period for claims in contract is six years in the UK. But when do the six years start running?

That is the question the court had to answer in Hirst v Dunbar. The construction works were completed in December 2012, payment demanded in March 2014 and legal proceedings issued in August 2019.  Accordingly, limitation would be a problem if time started running when the work was completed but not if the six years ran from the date of the demand.

In the event, the claim failed because there was no contract in place. However, the court went on to consider the limitation point and give some helpful guidance on an issue that had not previously been ruled upon.

Mr Hirst relied on the Scheme for Construction Contracts, which set out a default payment mechanism when payment isn’t expressly dealt with in a contract. Paragraph 6 of the Scheme says that the payment of the contract price is 30 days after the completion of the works or the making of a claim, whichever is later.

In turn, Mr Hirst said that his right to be paid arose under paragraph 9 of the Scheme, which was when a payment notice should have been issued five days after the due date for payment.

The court disagreed. The starting point is that the right to be paid arose when the works were completed and clear wording is required to displace this presumption.  The Scheme didn’t amount to such wording.  The situation would be different if the contract required a further condition to be satisfied before the entitlement to payment was satisfied, such as the issue of a certificate by a party appointed to administer the contract.

One of the first things you learn as a law student is that the standard limitation period for claims in contract is six years in the UK. But when do the six years start running?
.

The Scheme didn’t have this effect, particularly as the payment mechanism was only engaged following a claim for payment. It would be unfair to let the receiving party stop time running for limitation purposes by delaying issuing a claim.

For one reason or another, there is often a considerable delay pursuing claims for payment in a construction context.  This case is a reminder that longstop date for doing so is likely to be six years after the work was done and that inventive arguments based on the Scheme are unlikely to assist.

About this article

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

About this article

Read, listen and watch our latest insights

art
  • 10 October 2024
  • Employment

Employment Rights Bill – the biggest changes for a generation

Today, 10 October 2024, the Government has unveiled their long-awaited Employment Rights Bill, fulfilling their election manifesto pledge to introduce major reform to workers’ rights within 100 days of government.

art
  • 10 October 2024
  • Employment

Prioritise mental health in the workplace – FAQs

Today is World Mental Health Day, and the focus this year is mental health at work.

art
  • 08 October 2024
  • Immigration

The Immigration Rules updates – October 2024

The Home Office has issued a statement of changes to the Immigration Rules, impacting UK immigration applications. Published on 10 September 2024, these changes take effect as of yesterday, 08 October 2024, with some set to be implemented in early 2025.

art
  • 08 October 2024
  • Employment

Hidden Disabilities in the Workplace: Chronic Pain

In this article we will consider guidance on how hidden disabilities can be managed in the workplace and what employers should consider specifically for employees suffering from chronic pain.

Pub
  • 08 October 2024
  • Public Procurement

Procurement Challenges under the Procurement Act 2023

Taking prompt advice is essential as unsuccessful bidders have just ten days within which to issue court proceedings if they want to benefit from the automatic suspension provided for in the Regulations, which prevents the contracting authority from awarding the contract to anyone else.

art
  • 03 October 2024

Clarkslegal receives outstanding results in Legal 500 guide

Clarkslegal thanks clients for exceptional feedback in its 2025 Legal 500 rankings. Clarkslegal is proud that Legal 500 has recognised the firm in the following areas: Construction, Litigation, Property, Corporate, Employment & Immigration.