Search

How can we help?

Icon

Does a construction contract require a final account mechanism?

The recent case of JSM Construction Limited v Western Power Distribution (West Midlands) plc [2020] considers whether construction contracts require a final account mechanism.

Payment under the Construction Act

If payment terms in a construction contract do not comply with The Housing Grants, Construction and Regeneration Act 1996 (the ‘Construction Act’), The Scheme for Construction Contracts (England and Wales) Regulations 1998 (the ‘Scheme’) implies payment terms.

Section 110 of the Construction Act requires that every construction contract provides an adequate mechanism for determining what payments become due under a construction contract and a final date for when those payments are to be made. However, the Scheme goes further and includes a final account provision.

In JSM Construction Limited v Western Power Distribution (West Midlands) PLC the court had to decide whether the contract between the parties, which did not contain an express final account mechanism, complied with the Construction Act and if not, whether the final account provision would be implied through the Scheme.

Facts on construction contract case

Western Power Distribution (West Midlands) Plc (‘WPD’) engaged JSM Construction Limited (‘JSM’) to install two cables and associated ductwork pursuant to a bespoke contract in 2016 (the ‘Contract’).

The Contract provided for interim payments, but there was no express final account mechanism.

Following completion of the works, JSM issued its final application for payment for £1.5 million. As no payment was made, JSM commenced proceedings on the basis that a term should be implied into the Contract to reflect paragraph 5 of the Scheme (that payment for a final account claim shall become due on the later of 30 days after completion of the works or the making of a claim by the payee). In response WPD contended that JSM’s entitlement under the Contract was limited to a series of interim payments only and there was no final account mechanism. It accordingly applied to strike out JSM’s claim or for summary judgment.

Decision

The main question to consider was whether the Contract provided an adequate mechanism for determining what payments become due under the Contract and when. If there was an adequate payment mechanism, the court confirmed there would be no need to imply a final account provision under the Scheme.

The Court confirmed that even though the Scheme contains a final account provision, the Construction Act does not necessarily require parties to include a separate provision for a final account in their construction contract for it to be compliant.  However, in this case there remained outstanding factual and legal disputes relating to insufficient design and the inadequacy of the contract pricing schedule, which made it unsuitable for summary determination.

Section 110 of the Construction Act requires that every construction contract provides an adequate mechanism for determining what payments become due under a construction contract and a final date for when those payments are to be made, and includes a final account provision.

Practical points to consider

This case highlights the differences between the Construction Act and the Scheme. If the minimum requirements of the Construction Act are not met the more prescriptive terms of the Scheme will be implied.

The case also indicates that not all construction contracts will need to include a separate final account clause to be adequate under the Construction Act.

Many construction contracts include a process for interim payment applications to be submitted in respect of an estimated value of the works, with the true value of the works to be determined at the final account stage. However, some construction contracts allow for a lump sum to be paid in stages with no final account process. In each case, it is a question of fact of whether a construction contract has an adequate payment mechanism.

If a construction contract does not provide a final account mechanism, contractors should ensure timely submittals of payment applications which accurately reflect the works progress, variations and claims or loss and expense that arise at the time of the payment application to avoid any entitlement to payment being lost. Employers should reject any payment application that is not a valid interim payment application. It is crucial that parties understand the specific payment procedures in their contracts, particularly any bespoke amendments.

About this article

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

About this article

Read, listen and watch our latest insights

art
  • 10 October 2024
  • Employment

Employment Rights Bill – the biggest changes for a generation

Today, 10 October 2024, the Government has unveiled their long-awaited Employment Rights Bill, fulfilling their election manifesto pledge to introduce major reform to workers’ rights within 100 days of government.

art
  • 10 October 2024
  • Employment

Prioritise mental health in the workplace – FAQs

Today is World Mental Health Day, and the focus this year is mental health at work.

art
  • 08 October 2024
  • Immigration

The Immigration Rules updates – October 2024

The Home Office has issued a statement of changes to the Immigration Rules, impacting UK immigration applications. Published on 10 September 2024, these changes take effect as of yesterday, 08 October 2024, with some set to be implemented in early 2025.

art
  • 08 October 2024
  • Employment

Hidden Disabilities in the Workplace: Chronic Pain

In this article we will consider guidance on how hidden disabilities can be managed in the workplace and what employers should consider specifically for employees suffering from chronic pain.

Pub
  • 08 October 2024
  • Public Procurement

Procurement Challenges under the Procurement Act 2023

Taking prompt advice is essential as unsuccessful bidders have just ten days within which to issue court proceedings if they want to benefit from the automatic suspension provided for in the Regulations, which prevents the contracting authority from awarding the contract to anyone else.

art
  • 03 October 2024

Clarkslegal receives outstanding results in Legal 500 guide

Clarkslegal thanks clients for exceptional feedback in its 2025 Legal 500 rankings. Clarkslegal is proud that Legal 500 has recognised the firm in the following areas: Construction, Litigation, Property, Corporate, Employment & Immigration.