Search

How can we help?

Icon

Delaying Challenging a Public Tender Award – Don’t Lose Your Rights!

Timing is critical to the success of a challenge to a public tender.

Typically, an unsuccessful bidder will receive a letter from the contracting body notifying them that they have not won the tender, what their scores were and what the scores of the successful bidder(s) were.  Assuming it is an above threshold tender, they will also be told that the contracting body will allow a ten-day standstill period before they enter into the contract with the winning bidder.   That is ten actual days, rather than ten working days. So, once you have taken into account weekends and bank holidays, the actual time available could be five working days or possibly less.

In that short period, the unsuccessful bidder has to deal with the disappointment of losing, review in detail exactly why it lost and why the successful bidder won and decide whether to challenge the tender award.  The law on procurement challenges is not straightforward and this will often require the unsuccessful bidder to take legal advice.  Allowing time for all that to happen can take you to the very end of the ten-day standstill period.  That is not necessarily a problem as it is usually possible to agree an extension to the standstill period with the contracting authority to allow them time to review and respond to your procurement challenge, rather than heading straight to Court.

However, there is a very important deadline which all bidders must keep firmly in mind throughout this period – the 30-day rule.  Regulation 92(2)  of the Public Contracts Regulations 2015 states that “… proceedings must be started within 30 days beginning with the date when the economic operator [i.e. the bidder] first knew or ought to have known that grounds for starting the proceedings had arisen”.

If 30 days passes from the date of you receiving the Contract Award Letter (or otherwise first becoming aware of the ground of challenge) and you have not taken action to preserve your claim, such as issuing court proceedings, it is likely to be very difficult for you to avoid your claim being statute barred.

The importance of reacting and taking legal action without delay has been re-emphasised by the Court in the recent case, Riverside Truck Rental Limited v Lancashire County Council (2020 EWHC 1018). In that case, Riverside Truck received notification from Lancashire County Council on 29 November 2019 that they had been unsuccessful in the tender for supply of tractor cabs and trailers and, in fact, had been disqualified. A few days later, on 2 December 2019, Riverside Truck wrote to the Council disputing the tender outcome and saying they would legally challenge the award if their bid was not considered.  After further correspondence, the Council agreed to extend the standstill period, but only until 12 December 2019 (i.e. from 9 December 2019).

The matter was not resolved, and Riverside Truck issued Court proceedings but not until 24 January 2020.  The 30-days under Regulation 92(2) had expired on 30 December 2019 at the latest, so the proceedings were issued over three weeks after the deadline had expired.

Riverside Truck made an application to the Court for an extension of time to allow them to sue the Council after the 30 days had expired and provided multiple arguments as to why the application should be granted.  Unfortunately for Riverside Truck, all were rejected by the Court.  The unsuccessful arguments included:

  1. The 30-day period coincided with the Christmas and Holiday period which made issuing in time more difficult.
  2. Riverside Truck had acted reasonably in spending the first week of the 30-day period trying to reach an amicable resolution with the Council so should be allowed more time to issue proceedings
  3. Riverside Truck did not have all the information it needed to fully formulate its challenge until 10 January 2020. The missing information was the winning bidder’s contract price which Riverside Truck say they needed to determine whether they would have won the challenge. The Court held that time started to run for the claim when they first became aware that the Council had breached the Regulations, not when they had all the information they needed to fully present their case.
  4. The Council should have realised that Riverside Truck were mistaken in believing they had longer than the 30 days under Regulation 92(2) to issue legal proceedings and should have told them. The Court held there was no obligation on the Council to point out legal mistakes made by Riverside Truck.
  5. That there was a public interest in allowing the claim to proceed to ensure that the Council obtained best-value for money and awarded the contract to a local company. If Truck Rentals bid had won, their contract price was £1million lower than the successful bidder. The Court held that a procurement challenge is a private claim by the bidder rather than a public challenge, such as a judicial review, and that this was not outweighed by the public interest in protecting the rapid process for the award of public contracts which a strict enforcement of time limit would support.

The Court rejected all of Riverside Truck’s arguments meaning that their procurement challenge is now statute-barred.

Although timing is critical when challenging a tender award, there is always sufficient time for a well-organised bidder to take the necessary action to overturn and correct an incorrect tender award or any other mistake made by a contracting authority.

If you receive a letter notifying you that your bid has been unsuccessful, the following practical tips are advisable:

Review the contract award with your bidding team to establish whether your bid (and the winning tenderer’s bid, as far as possible) has been evaluated correctly. Points to check included:

  1. Has the contracting authority understood the answers and information given in your bid correctly?
  2. Has the contracting authority applied the marking scheme correctly?
  3. Have you lost marks for failing to address issues which were not included in the tender questions?
  4. Basic mathematical errors in the calculation and weighting of marks?

If 30 days passes from the date of you receiving the Contract Award Letter, it is likely to be very difficult for you to avoid your claim being statute barred.

Assess whether you have all the information you need from the contracting authority to determine whether they have correctly evaluated your bid.

Given the short time available, consider taking legal advice at the outset.

Present your challenge in writing, including requesting further information and seeking an extension to the Standstill Period if necessary.

Don’t delay and keep a careful eye on deadlines!

Clarkslegal’s procurement team has considerable experience in advising clients on challenges to tender awards and is often able to resolve mistakes in the evaluation process through correspondence with the public body without the need for expensive legal proceedings.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 03 November 2026
  • Commercial Real Estate

Ban on upwards-only rent reviews: What can landlords of 1954 Act protected leases do?

The commencement of the English Devolution and Community Empowerment Act (the Act) poses a real threat to the interests of landlords whose business tenants are protected under the Landlord and Tenant Act 1954 (LTA) (as well as those that are outside the LTA).

art
  • 29 October 2026
  • Immigration

UK Immigration shake-up: More flexibility for skilled workers, but at what cost?

The UK Government has outlined further changes to its immigration system, with new measures affecting international graduates, sponsored workers, and businesses employing overseas talent.

art
  • 28 October 2026
  • Privacy and Data Protection

Remote working: 5 key data protection risks for employers

Remote working has become more prominent in modern business. While flexible working arrangements can improve productivity and employee wellbeing, they also create new data protection risks. Regardless of the physical location in which work is done, compliance with UK GDPR does not change.

art
  • 27 October 2026
  • Employment

Fire and Rehire update: Key changes delayed

The Government has published two documents giving key updates to the anticipated changes around ‘fire and rehire’ and restricted contractual variations, coming about as a result of the Employment Rights Act 2025 (“ERA 2025”). We now understand that these changes will now be delayed to March, rather than January 2027.

art
  • 26 October 2026
  • Corporate and M&A

Shareholders’ Agreements for Founders and Investors – SHA Series Part 3 of 5

A shareholders’ agreement is arguably one of the most valuable corporate governance agreements (along with articles of association) in any private UK company with more than one shareholder.

art
  • 23 October 2026
  • Litigation and dispute resolution

Section 172 Companies Act 2006: Key lessons from Saxon Woods v Costa

The Supreme Court’s decision in Saxon Woods v Costa UKSC 21 clarifies directors’ duties under Section 172 Companies Act 2006, confirming that good faith requires both honest belief and appropriate conduct.