Search

How can we help?

Icon

An uncertain future for Smash & Grab adjudication

A recent decision in the Technology and Construction Court has prompted the industry to once again reflect on the well-documented cases of ISG v Seevic and Harding v Paice, from which the phrase “Smash & Grab” adjudication was born. You can find our commentary on those two cases here, and below we summarise why it appears that a change may be on the horizon.

For those unfamiliar with the term, a “Smash & Grab” adjudication involves one party to a construction contract claiming payment from another in circumstances where:

  • The claiming party has previously made an interim application for payment; and
  • The paying party has failed to issue either a payment or a pay less notice in respect of that interim application.

The amount claimed in the interim application is therefore deemed (for interim purposes at least) to be accepted by the paying party as the true value of the relevant works. The paying party must pay the full amount and is not entitled to challenge the proper valuation of the application, regardless of whether they dispute it.

This position has now been reconsidered in Imperial Chemicals Industries Ltd v Merit Merrell Technology Ltd [2017].

The Facts

This case was a melting pot of legal issues, one being whether ICI could recover a perceived overpayment in respect of two previously adjudicated MMT interim applications.

ICI employed MMT on NEC3 terms for the provision of piping at a new paint manufacturing plant, but subsequently sought to terminate the contract by acceptance of MMT’s repudiatory breach. Unfortunately for ICI, the court later determined that MMT had committed no such breach, and in fact, that ICI had affected repudiation by wrongfully seeking to terminate.

To top things off, ICI had been ordered to pay over £8m to MMT following two successful smash and grab adjudications, an amount ICI believed to be in excess of the true value of the works. The question at hand was whether ICI could, after their repudiation, make a recovery of the perceived overpayment.

The Argument Against

MMT sought to apply the principles of ISG v Seevic and argued that in the absence of proper notices, the amounts paid by ICI were in fact the deemed value of the relevant works. They went further to suggest that as a consequence of the repudiation, ICI had lost its right of recovery. As such, the decisions in each adjudication were both final and binding on the parties, and could not be revisited.

The amount claimed in the interim application is therefore deemed (for interim purposes at least) to be accepted by the paying party as the true value of the relevant works.

The Decision

The court disagreed with MMT’s argument and noted that a party’s existing rights would survive the termination of a contract by repudiation. ICI was therefore entitled to challenge the true assessment of the value of the works, and to recovery of any overpayments.

More interesting were the comments of Fraser J in reaching that conclusion, who said that the decisions in ISG v Seevic and Harding v Paice were “difficult to reconcile” with each other. He went on to suggest there was “real doubt” that ISG v Seevic would be decided in the same way now. In doing so, Fraser J cast similar doubt over whether the current assumption that paying parties who have failed to serve a payment or pay less notice cannot challenge the value of works in a second adjudication is correct.

Comment

The implications of Fraser J’s commentary are not to end a contractor’s entitlement to adjudicate for payment in the absence of a proper payment notice. That would be to contradict the government’s intention to encourage cashflow. They do however open the door to the possibility of cross-adjudications, whereby paying parties could seek the proper assessment of the true value of works claimed under a contractor’s interim application.  We wait for further guidance from the TCC, and perhaps the Court of Appeal, on ISG v Seevic and the future of “Smash and Grab”.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 16 December 2025
  • Employment

Christmas Parties – Festive Fun or a New Year Hangover?

It’s Christmas party season! The office party is often a mixed blessing – an opportunity to boost morale and perhaps celebrate a successful year yet also a melting pot of workers letting their hair down, with potential for accidents, injuries, threats and claims.

art
  • 10 December 2025
  • Privacy and Data Protection

The 12 Data Protection Mistakes of Christmas

As the festive season approaches, it is not just last-minute shopping and office parties that can catch organisations off guard; data protection slip-ups are just as common.

Pub
  • 04 December 2025
  • Immigration

UK Immigration: What to expect in 2026 for employers

Join our UK immigration specialists, Ruth Karimatsenga and Monica Mastropasqua, as they explore the key updates and how they affect your business in 2026.

Pub
  • 04 December 2025
  • Corporate and M&A

Autumn Budget 2025 Breakdown: Key takeaways for business buyers and sellers

Join Stuart Mullins and Nicky Goringe Larkin as they delve into the key updates from the Chancellor’s announcement, with a focus on what matters most for businesses looking to buy and sell.

art
  • 03 December 2025
  • Corporate and M&A

Why is carrying out a legal Due Diligence investigation necessary during an proposed acquisition?

Merging with or acquiring another company is a high-stakes endeavour. The purpose, process and common areas of investigation during a M&A transaction.

art
  • 02 December 2025
  • Employment

All I Want for Christmas… Is No Tribunal Claims!

Before the festivities begin, it is worth unwrapping the key risks and understanding how employers can protect their staff, their reputation and their sanity, while still delivering a thoroughly enjoyable evening.