Search

How can we help?

Icon

Adjudication decision cannot be used to resist prior adjudication

In M Davenport v Greer, one of the first cases to follow the court of Appeal’s decision in S&T v Grove, the TCC held that an employer could not use a “true value” adjudication decision as a defence or set off to enforcement proceedings for an earlier decision in favour of the contractor.

Background

M Davenport Builders (MDB) carried out building work for the Greers under a contract which contained no provisions for payment and so the payment terms of the Scheme for Construction Contracts were implied into the contract.  When MDB issued a final account for £106,160.84, the Greers did not pay but failed to issue a payment or pay less notice.

MDB commenced an adjudication for the unpaid sum (plus interest) and was successful.  The Greers did not pay the sum awarded to MDB and instead commenced a second adjudication (before a different adjudicator) as to the true value of the works.  The adjudicator decided in favour of the Greers that no money was payable to MDB.

MDB brought enforcement proceedings to the TCC in respect of the unpaid award in the first adjudication decision.  The Greers defended the proceedings on the basis that the decision in the second adjudication could be used as a set-off or counterclaim.

Decision

Stuart-Smith J held that the Greers could not rely on the decision in the second adjudication as a ground to avoid paying the sum awarded in the first adjudication.  He followed the reasoning of S&T v Grove  that the first “smash and grab” adjudication created an immediate obligation to make payment, which had to be done before commencing a second adjudication as to the value, and on that basis held that because the Greers had failed to discharge that obligation, they could not rely on the result of the second adjudication to resist enforcement of the first decision.

Although S&T v Grove related to interim applications, Stuart-Smith J found no significant reason to justify a difference in approach for a final application, on the basis that deprivation of cashflow could have serious effects for a contractor whether it occurred during or at the end of the works.

However, although the decision in S&T v Grove was clear that payment was required before a true value adjudication could be commenced, Stuart-Smith J did not determine any issue relating to the jurisdiction of the second adjudicator, on the basis that the question of jurisdiction for the second adjudication did not need to be determined given that he had held that the Greers could not rely on the decision in that adjudication.  Instead, citing Harding v Paice [2015] EWCA Civ 1231, he noted that in that case a party discharging its payment obligation from a first adjudication was not a prerequisite to that party commencing a second adjudication.

This element of the decision does not entirely follow S&T v Grove, which held that the payment obligation must be discharged before the second adjudication can be commenced.  Despite finding that there was no distinction between the interim and final payment contexts, by not applying Grove to the issue of jurisdiction of the second adjudication, Stuart-Smith J implicitly creates a distinction i.e. that Grove fetters the right to adjudicate in the case of interim payments, but not for final payments.

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Practical implications

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Whilst the principle makes sense, however, questions remain over whether it is commercially practical, particularly in light of the decision that the second adjudicator will not necessarily lack jurisdiction (which means that the second adjudication may be able to proceed, and be relied upon and enforced, but only once the payment awarded in the first adjudication has been made).  It is not obvious why an employer should be obliged to pay the sum from the first adjudication when they already have a further decision that that sum is not the true value and so is not due to be paid.  All that will happen in those circumstances is that the employer has to pay the sum awarded in the first adjudication and then commence enforcement proceedings to recover it on the basis of the second decision, instead of dealing with both decisions by means of set-off.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

Pub
  • 09 November 2026
  • Corporate and M&A

Key Provisions found in a Shareholders’ Agreement – Episode 2

Explore the key provisions found in a shareholders’ agreement, including shareholder rights, share transfers, decision-making powers, dispute resolution and minority protections. Listen to Episode 2 of the Clarkslegal podcast for practical guidance.

art
  • 06 November 2026
  • Employment

New Sexual Harassment Prevention Duty: EHRC Guidance on Taking ‘All Reasonable Steps’

Following the changes brought into force by the Employment Rights Act 2025 on 30 October 2026, the Equality and Human Rights Commission (EHRC) has updated its technical guidance on preventing workplace sexual harassment, incorporating the changes imposed by the strengthened “all reasonable steps” preventative duty.

art
  • 03 November 2026
  • Commercial Real Estate

Ban on upwards-only rent reviews: What can landlords of 1954 Act protected leases do?

The commencement of the English Devolution and Community Empowerment Act (the Act) poses a real threat to the interests of landlords whose business tenants are protected under the Landlord and Tenant Act 1954 (LTA) (as well as those that are outside the LTA).

art
  • 29 October 2026
  • Immigration

UK Immigration shake-up: More flexibility for skilled workers, but at what cost?

The UK Government has outlined further changes to its immigration system, with new measures affecting international graduates, sponsored workers, and businesses employing overseas talent.

art
  • 28 October 2026
  • Privacy and Data Protection

Remote working: 5 key data protection risks for employers

Remote working has become more prominent in modern business. While flexible working arrangements can improve productivity and employee wellbeing, they also create new data protection risks. Regardless of the physical location in which work is done, compliance with UK GDPR does not change.

art
  • 27 October 2026
  • Employment

Fire and Rehire update: Key changes delayed

The Government has published two documents giving key updates to the anticipated changes around ‘fire and rehire’ and restricted contractual variations, coming about as a result of the Employment Rights Act 2025 (“ERA 2025”). We now understand that these changes will now be delayed to March, rather than January 2027.