Search

How can we help?

Icon

Adjudication decision cannot be used to resist prior adjudication

In M Davenport v Greer, one of the first cases to follow the court of Appeal’s decision in S&T v Grove, the TCC held that an employer could not use a “true value” adjudication decision as a defence or set off to enforcement proceedings for an earlier decision in favour of the contractor.

Background

M Davenport Builders (MDB) carried out building work for the Greers under a contract which contained no provisions for payment and so the payment terms of the Scheme for Construction Contracts were implied into the contract.  When MDB issued a final account for £106,160.84, the Greers did not pay but failed to issue a payment or pay less notice.

MDB commenced an adjudication for the unpaid sum (plus interest) and was successful.  The Greers did not pay the sum awarded to MDB and instead commenced a second adjudication (before a different adjudicator) as to the true value of the works.  The adjudicator decided in favour of the Greers that no money was payable to MDB.

MDB brought enforcement proceedings to the TCC in respect of the unpaid award in the first adjudication decision.  The Greers defended the proceedings on the basis that the decision in the second adjudication could be used as a set-off or counterclaim.

Decision

Stuart-Smith J held that the Greers could not rely on the decision in the second adjudication as a ground to avoid paying the sum awarded in the first adjudication.  He followed the reasoning of S&T v Grove  that the first “smash and grab” adjudication created an immediate obligation to make payment, which had to be done before commencing a second adjudication as to the value, and on that basis held that because the Greers had failed to discharge that obligation, they could not rely on the result of the second adjudication to resist enforcement of the first decision.

Although S&T v Grove related to interim applications, Stuart-Smith J found no significant reason to justify a difference in approach for a final application, on the basis that deprivation of cashflow could have serious effects for a contractor whether it occurred during or at the end of the works.

However, although the decision in S&T v Grove was clear that payment was required before a true value adjudication could be commenced, Stuart-Smith J did not determine any issue relating to the jurisdiction of the second adjudicator, on the basis that the question of jurisdiction for the second adjudication did not need to be determined given that he had held that the Greers could not rely on the decision in that adjudication.  Instead, citing Harding v Paice [2015] EWCA Civ 1231, he noted that in that case a party discharging its payment obligation from a first adjudication was not a prerequisite to that party commencing a second adjudication.

This element of the decision does not entirely follow S&T v Grove, which held that the payment obligation must be discharged before the second adjudication can be commenced.  Despite finding that there was no distinction between the interim and final payment contexts, by not applying Grove to the issue of jurisdiction of the second adjudication, Stuart-Smith J implicitly creates a distinction i.e. that Grove fetters the right to adjudicate in the case of interim payments, but not for final payments.

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Practical implications

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Whilst the principle makes sense, however, questions remain over whether it is commercially practical, particularly in light of the decision that the second adjudicator will not necessarily lack jurisdiction (which means that the second adjudication may be able to proceed, and be relied upon and enforced, but only once the payment awarded in the first adjudication has been made).  It is not obvious why an employer should be obliged to pay the sum from the first adjudication when they already have a further decision that that sum is not the true value and so is not due to be paid.  All that will happen in those circumstances is that the employer has to pay the sum awarded in the first adjudication and then commence enforcement proceedings to recover it on the basis of the second decision, instead of dealing with both decisions by means of set-off.

About this article

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

About this article

Read, listen and watch our latest insights

art
  • 02 July 2025
  • Employment

Day One Rights: What the New UK Employment Bill Means for You and Your Workplace

Let’s unpack what’s changing in the UK Employments Rights Bill, and why it matters, and what both employees and employers should expect.

art
  • 01 July 2025
  • Privacy and Data Protection

Data protection compliance: tricky issues for employers

This article highlights key issues organisations may face when processing personal data and stresses the importance of a proactive approach. It also outlines tailored training packages to support compliance and build internal expertise.

art
  • 26 June 2025
  • Employment

A shift in EHRC guidance on single sex spaces in the workplace

In a recent significant shift, the Equality and Human Rights Commission (“the EHRC”) has quietly amended its guidance on single sex spaces in the workplace.

art
  • 25 June 2025
  • Immigration

Immigration Changes in Statement HC 836 – what do they mean?

The UK government has released its latest Statement of Changes to the Immigration Rules (HC 836), with shocking implementation dates throughout July 2025.

art
  • 20 June 2025
  • Privacy and Data Protection

Data Protection reform receives Royal Assent: What is the Data (Use and Access) Act 2025 (DUAA) and what it means for your business

The UK’s data protection framework is about to undergo its most significant change since the UK GDPR came into force. After months of parliamentary debate, the Data (Use and Access) Act 2025 (‘DUAA’) has successfully received Royal Assent.

art
  • 18 June 2025
  • Employment

Pride Month: How Can You Celebrate as an Employer

The UK held its first Pride Parade in 1972, inspired by events held in major American cities following the Stonewall rebellion in New York in June 1969.