Search

How can we help?

Icon

Termination: the pitfalls

There are many risks in terminating a contract, particularly in construction contracts – get it wrong and you risk being in breach of contract yourself. The two main pitfalls are:

  • Not having valid ground for termination (these can be very limited), and
  • Not giving the right notices.

The Contract

The starting point is the terms of the contract which will usually set out the grounds and process for, and the effect of termination. The standard form contracts tend to have various grounds for termination, which often include:

  • Non-payment by the employer
  • Specified defaults, g. failure to proceed regularly and diligently with the works and breach of certain contract provisions
  • Specified events, e.g. force majeure
  • Insolvency

It is unusual to find a clause in domestic construction contracts that entitles an employer to terminate just because it wants to i.e. “termination for convenience”. These can sometimes appear in consultants’ appointments. However, if the motive behind termination is to get someone else to do the same work for a better price, the terminating party risks being in breach of contract.

The contract also normally describes a specific process to effect termination. The JCT form provides for a two-notice procedure.  The first is a warning notice notifying the default and giving the defaulting party an opportunity to remedy.  The second is a notice of termination.  Any notices should be given exactly in accordance with the requirements of content (i.e. set out the basis of the default) and method of delivery.

Failure to comply with such notices is likely to prevent termination being valid. The contract may also impose limits on the right to termination i.e. that it should be reasonable or in good faith. For example, the JCT form says that a notice to terminate should not be given “unreasonably or vexatiously”.  This is normally a basis of challenge by the party that has been terminated.

Common Law Termination (non-contractual)

Unless the contract expressly excludes it, there is also a separate right at common law to terminate if there is a fundamental breach of contract.  This is called repudiation. However, establishing repudiation is not straightforward and it depends on the nature of the breach. It may also depend on what the contract says. It must be enough to demonstrate that one party no longer intends to be bound by the contract. The terminating party (here the “innocent party”) must demonstrate the breach justified termination. In this situation, it takes two to end the contract and the innocent party can choose whether to ignore the breach or accept it and bring the contract to an end and claim damages.

Do you have to choose between contract and repudiation?

This is a complex area and in certain circumstances, you can try to enforce both.  You should consider your position carefully before exercising your right to terminate and assess the risks of choosing one option over the other or trying to pursue both.

Also, if you try to serve notice of termination under the contract and you get it wrong, you risk being in repudiation yourself. This will entitle the other party to accept the repudiation (i.e. bring the contract to an end) and claim damages.

The consequences of termination

The contract will usually set out the consequences of termination and its effect on payment.

This was relevant in the recent case of Almacantar (Centre Point) Ltd v Sir Robert McAlpine Ltd (2018) which related to works carried out under a pre-construction services agreement at the Centre Point tower in London.  The contractor had completed all its services but the parties decided not to proceed to the second stage and the contract was terminated by mutual agreement.  There was a subsequent argument about the contractor’s entitlement to 50% of its fee which the agreement stated was payable if the parties entered into a construction contract.   The court held that the contractor was not entitled to this because the clauses dealing with payment on termination did not provide for it.  In this case the contractor should have ensured that all material terms of the termination (including payments) should have been agreed and recorded in the agreement to terminate.

The starting point is the terms of the contract which will usually set out the grounds and process for, and the effect of termination.

Points to consider

As termination is a risky business here are some points to consider: 

  • Does the contract have to end? Consider whether you can manage and/or take steps to improve the relationship. Often early advice in this regard can help save time and money later.
  • Check the contract and comply with the terms. Again, obtaining early advice can ensure money isn’t wasted in dealing with problems later in the process.
  • Can you hedge your bets? i.e. exercise contractual right to termination and elect to accept repudiation?
  • Draft any notices carefully: State the grounds and refer to the contractual
  • provision and/or repudiation and ensure that you check the method of delivery.
  • If you are the party being terminated, check that it is on valid grounds, contractual requirements have been complied with and whether you can object (i.e. has the other party acted unreasonably?).

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

Pub
  • 07 September 2026
  • Corporate and M&A

Frequently Asked Questions About Shareholders’ Agreements – Episode 1

Join Emma Docking and Jonathan Hayes as they explore some of the most frequently asked questions about shareholders’ agreements, including what they are, how they work alongside articles of association, and the risks of operating without one.

art
  • 03 September 2026
  • Employment

Employment Rights Act – October Changes

We are well and truly underway with implementation of the Employment Rights Act 2025 (“ERA 2025”) and October brings the next tranche of changes that employers will need to be ready for.

art
  • 02 September 2026
  • Immigration

Mandatory MFA for Sponsor Management System Users: What Sponsors Need to Know

The Home Office is introducing a significant security change to the Sponsor Management System (SMS). From 3 September 2026, the Home Office will begin a phased rollout of mandatory Multi-Factor Authentication (MFA) for SMS users.

art
  • 01 September 2026

Orwins continues growth with investment in Milners and Acquisition of Roe Lawyers

Clarkslegal is pleased to share the news that Orwins, the legal services group we joined earlier this year, has announced a significant investment in Yorkshire law firm Milners and the acquisition of London-based specialist practice Roe Lawyers.

Pub
  • 28 August 2026
  • Immigration

Right to Work and Sponsor Licence Changes 2026: Key dates for businesses

In this podcast, immigration solicitors Ruth Karimatsenga and Monica Mastropasqua discuss the key immigration compliance changes coming into force in September and October 2026 and what employers, HR teams, sponsors and individuals should do to prepare.

art
  • 28 August 2026
  • Commercial Real Estate

Modernising security of tenure: The Law Commission’s follow up consultation paper

On 16th June 2026, the Commission published its second consultation paper: Business Tenancies: the right to renew – modernising security of tenure.