Search

How can we help?

Icon

How do I prove my final account claim?

Many construction disputes relate to the calculation of the final account. Sometimes there may be an interesting point of law or expert evidence at stake.  More often than not, the dispute will boil down to proving what work was done and / or what was the agreed price for the work.

These issues came into play in the recent case of Premier Engineering (Lincoln) Limited v MW High Tech Project UK Limited. The underlying project was very large (£150m) but Premier started work on a very small subcontract. When MW fell out with another subcontractor Premier agreed to supply additional labour to help MW the project back on track.  The work was carried out on an ad hoc basis – MW told Premier each week what work was required, Premier did the work and invoiced according to its timesheets. Come the end of the project, the parties were unable to agree Premier’s final account.  Premier claimed an additional £1.3m, whereas MW said that it had already overpaid.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The labour charges represented by far the largest part of the claim.  Premier’s claim relied on its timesheets that had been signed each week by an authorised MW representative.  MW sought to distance itself from the timesheets for two reasons. Firstly, it said that it signed the timesheets without carefully checking them ‘to keep the peace’.  Secondly, the turnstile records at site suggested that the hours worked were lower than claimed.  The Judge rejected both arguments.

Signed timesheets are primary evidence that work has been done. It was MW’s own fault if it had not adequately resourced the job to check the timesheets before signing them off.  This was the best opportunity for MW to raise any concerns about the sums claimed. In any event, MW had challenged the timesheets from time to time.

Turnstile data could have been relevant evidence.However, in this case Premier had raised concerns about the turnstiles – sometimes they were not working and on other occasions Premier’s operatives were working outside the area covered by the turnstiles. The Judge concluded that the parties had agreed that the turnstile data would not be taken into account. They agreed instead to use a biometric clock but this was not installed on site until a later date.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The materials claim threw up a different challenge.  About £100k turned on the claim but it covered very many individual invoices, some of which were low value.  It would not have been realistic for the court to consider every invoice.  Instead it applied a ‘materiality threshold’ to exclude the lowest value invoices. It examined a representative sample of the remainder and used the conclusions on these to determine what was due under the entire batch of invoices.

The case is good illustration of how the court will approach such a claim and the challenges of determining a final account that it for a large sum but made up of very small items.  It also emphasises the importance the claiming party keeping contemporaneous records and the paying party raising objections at the time.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 18 August 2026
  • Immigration

Home Office curtailment of Sponsored Workers’ permission: Why employers and employees must act quickly

The Home Office has recently changed the speed at which it processes sponsor notifications following the end of a sponsored worker’s employment.

art
  • 13 August 2026
  • Employment

ACAS Draft New Code on Disciplinary and Grievance Procedures

ACAS have published a draft Code on 30 July 2026, which will replace the 2015 ACAS Code on disciplinary and grievance procedures when the Code is finalised at the end of September 2026.

art
  • 12 August 2026
  • Corporate and M&A

EMIs – April 2026 changes explained

On 6 April 2026 the Enterprise Management Incentive scheme (EMI) was expanded to make EMIs accessible to a wider range of businesses.

art
  • 06 August 2026
  • Privacy and Data Protection

The rise of the AI-powered individual: Is your business ready?

Artificial intelligence is changing the data protection landscape, but perhaps not in the way many organisations expected. Much of the discussion has centred on businesses adopting AI and ensuring they comply with the UK GDPR.

Pub
  • 06 August 2026
  • Employment

Employment law changes in 2026: What you need to know

With ongoing changes to UK employment law, staying updated is more challenging than ever. Join Monica Atwal and Harry Berryman for a live webinar covering 2026 HR changes and key employment law updates on Thursday 17 September.

Pub
  • 04 August 2026
  • Employment

From Opportunity to Employment: Building Inclusive Workplaces Together | Hosted by Breakthrough Supported Employment

Join Breakthrough Supported Employment for a live seminar on building inclusive workplaces at Malmaison Reading. Clarkslegal’s Lucy White will speak alongside industry experts, sharing insights on fostering diversity and creating equitable opportunities.