Search

How can we help?

Icon

How do I prove my final account claim?

Many construction disputes relate to the calculation of the final account. Sometimes there may be an interesting point of law or expert evidence at stake.  More often than not, the dispute will boil down to proving what work was done and / or what was the agreed price for the work.

These issues came into play in the recent case of Premier Engineering (Lincoln) Limited v MW High Tech Project UK Limited. The underlying project was very large (£150m) but Premier started work on a very small subcontract. When MW fell out with another subcontractor Premier agreed to supply additional labour to help MW the project back on track.  The work was carried out on an ad hoc basis – MW told Premier each week what work was required, Premier did the work and invoiced according to its timesheets. Come the end of the project, the parties were unable to agree Premier’s final account.  Premier claimed an additional £1.3m, whereas MW said that it had already overpaid.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The labour charges represented by far the largest part of the claim.  Premier’s claim relied on its timesheets that had been signed each week by an authorised MW representative.  MW sought to distance itself from the timesheets for two reasons. Firstly, it said that it signed the timesheets without carefully checking them ‘to keep the peace’.  Secondly, the turnstile records at site suggested that the hours worked were lower than claimed.  The Judge rejected both arguments.

Signed timesheets are primary evidence that work has been done. It was MW’s own fault if it had not adequately resourced the job to check the timesheets before signing them off.  This was the best opportunity for MW to raise any concerns about the sums claimed. In any event, MW had challenged the timesheets from time to time.

Turnstile data could have been relevant evidence.However, in this case Premier had raised concerns about the turnstiles – sometimes they were not working and on other occasions Premier’s operatives were working outside the area covered by the turnstiles. The Judge concluded that the parties had agreed that the turnstile data would not be taken into account. They agreed instead to use a biometric clock but this was not installed on site until a later date.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The materials claim threw up a different challenge.  About £100k turned on the claim but it covered very many individual invoices, some of which were low value.  It would not have been realistic for the court to consider every invoice.  Instead it applied a ‘materiality threshold’ to exclude the lowest value invoices. It examined a representative sample of the remainder and used the conclusions on these to determine what was due under the entire batch of invoices.

The case is good illustration of how the court will approach such a claim and the challenges of determining a final account that it for a large sum but made up of very small items.  It also emphasises the importance the claiming party keeping contemporaneous records and the paying party raising objections at the time.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 13 November 2026
  • Immigration

UK Immigration Reform: The End of the 5-Year Settlement Route and the threat of legal action

The UK Government’s proposed changes to Indefinite Leave to Remain (ILR) have sparked growing concern among migrants, employers, and immigration professionals, with a potential legal challenge now being considered.

Pub
  • 09 November 2026
  • Corporate and M&A

Key Provisions found in a Shareholders’ Agreement – Episode 2

Explore the key provisions found in a shareholders’ agreement, including shareholder rights, share transfers, decision-making powers, dispute resolution and minority protections. Listen to Episode 2 of the Clarkslegal podcast for practical guidance.

art
  • 06 November 2026
  • Employment

New Sexual Harassment Prevention Duty: EHRC Guidance on Taking ‘All Reasonable Steps’

Following the changes brought into force by the Employment Rights Act 2025 on 30 October 2026, the Equality and Human Rights Commission (EHRC) has updated its technical guidance on preventing workplace sexual harassment, incorporating the changes imposed by the strengthened “all reasonable steps” preventative duty.

art
  • 03 November 2026
  • Commercial Real Estate

Ban on upwards-only rent reviews: What can landlords of 1954 Act protected leases do?

The commencement of the English Devolution and Community Empowerment Act (the Act) poses a real threat to the interests of landlords whose business tenants are protected under the Landlord and Tenant Act 1954 (LTA) (as well as those that are outside the LTA).

art
  • 29 October 2026
  • Immigration

UK Immigration shake-up: More flexibility for skilled workers, but at what cost?

The UK Government has outlined further changes to its immigration system, with new measures affecting international graduates, sponsored workers, and businesses employing overseas talent.

art
  • 28 October 2026
  • Privacy and Data Protection

Remote working: 5 key data protection risks for employers

Remote working has become more prominent in modern business. While flexible working arrangements can improve productivity and employee wellbeing, they also create new data protection risks. Regardless of the physical location in which work is done, compliance with UK GDPR does not change.