Search

How can we help?

Icon

Claims for payment – when is it too late?

One of the first things you learn as a law student is that the standard limitation period for claims in contract is six years in the UK. But when do the six years start running?

That is the question the court had to answer in Hirst v Dunbar. The construction works were completed in December 2012, payment demanded in March 2014 and legal proceedings issued in August 2019.  Accordingly, limitation would be a problem if time started running when the work was completed but not if the six years ran from the date of the demand.

In the event, the claim failed because there was no contract in place. However, the court went on to consider the limitation point and give some helpful guidance on an issue that had not previously been ruled upon.

Mr Hirst relied on the Scheme for Construction Contracts, which set out a default payment mechanism when payment isn’t expressly dealt with in a contract. Paragraph 6 of the Scheme says that the payment of the contract price is 30 days after the completion of the works or the making of a claim, whichever is later.

In turn, Mr Hirst said that his right to be paid arose under paragraph 9 of the Scheme, which was when a payment notice should have been issued five days after the due date for payment.

The court disagreed. The starting point is that the right to be paid arose when the works were completed and clear wording is required to displace this presumption.  The Scheme didn’t amount to such wording.  The situation would be different if the contract required a further condition to be satisfied before the entitlement to payment was satisfied, such as the issue of a certificate by a party appointed to administer the contract.

One of the first things you learn as a law student is that the standard limitation period for claims in contract is six years in the UK. But when do the six years start running?
.

The Scheme didn’t have this effect, particularly as the payment mechanism was only engaged following a claim for payment. It would be unfair to let the receiving party stop time running for limitation purposes by delaying issuing a claim.

For one reason or another, there is often a considerable delay pursuing claims for payment in a construction context.  This case is a reminder that longstop date for doing so is likely to be six years after the work was done and that inventive arguments based on the Scheme are unlikely to assist.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 02 April 2026
  • Commercial Real Estate

Can I have access to a neighbour’s land to carry out works to my property?

As a landowner, maintaining and repairing your property is important. It may be the case that to do so, you will need to access the land of a neighbour.

art
  • 01 April 2026
  • Privacy and Data Protection

Recognising DSARs: top tips for organisations

The UK GDPR grants Data Subjects, who are the individuals to whom the personal data relates, rights over their personal data, including the rights of access, correction and erasure.

art
  • 30 March 2026
  • Employment

Legislative Changes – What Employers Need to Know for April 2026

With the phased implementation of the Employment Rights Act 2025 (ERA), alongside other legislative updates, April 2026 brings a wide range of important changes for employers.

Pub
  • 27 March 2026
  • Corporate and M&A

Shareholder Disputes: What to do when disputes arise – Episode 4

Join Stuart Mullins and Jack Hobbs for episode four of our Shareholder Disputes podcast series as they confront the realities of shareholder fallouts and share practical strategies for managing these complex situations.

art
  • 24 March 2026
  • Immigration

Spouse Visa – Is your relationship genuine and subsisting?

For years many couples have become frustrated by the requirements for a spouse visa as the rules and guidance are difficult to understand. A significant amount of applications are rejected on the basis of the applicant not providing the adequate documents to evidence the relationship requirement.

art
  • 20 March 2026
  • Corporate and M&A

Drag-Along & Tag-Along Rights: Why Every Company Needs Them

When starting a company, very few founders are aware of the potential issues around shares, share ownership and the implications of that when selling their company.