NEC4: enhancing NEC3
- 26 April 2017
- Construction
NEC has published a paper summarising the changes called “NEC4: The next generation – An explanation of changes and benefits” which can be accessed here. We have highlighted the key changes below.
Two new contracts
This combines design, construction, operation and/or maintenance from a single supplier.
This will be issued in consultation form initially and is intended to suit clients who want to enter into a single collaborative contract with a number of participants. NEC says that “the basis of the contract will be that all parties work together in achieving Client objectives, and share in the risks and benefits of doing so”.
New features
Changes have been made to the core and secondary options with a clear aim to reduce the need for negotiated Z clauses.
New core options
Incorporates the requirements imposed by the Bribery Act as well as a right to terminate if a corrupt act is carried out.
NEC4 contracts (except short ones) will include confidentiality clauses with the purpose being to restrict the disclosure of confidential project information.
Includes a clause that gives either party the right to assign the benefit of the contract.
New secondary options
Includes provisions specifically to support design and build contracting. A key element of this is the inclusion of the obligation on the contractor to maintain PI Insurance. Further, the Contractor’s design duty has also been aligned with the industry standard preferred by insurers, that is to use the skill and care normally used by professionals designing similar works.
The ECC now includes a dispute avoidance option (W3), applicable if adjudication does not apply, to refer a dispute to a DAB nominated by the parties when the contract is formed. The Adjudicator’s Contract has been changed so it can be used to appoint board members and has been renamed Dispute Resolution Service Contract.
The ECC now incorporates ECI clauses previously published by NEC in 2015.
Includes provisions in ECC specifically to support the use of BIM.
The Client will have the option to request the various warranties it requires in the form that they require without the need for Z clause amendments.
NEC has published a paper summarising the changes called “NEC4: The next generation – An explanation of changes and benefits”
Keep up to date with the latest tips, analysis and upcoming events by our legal experts, direct to your inbox.
Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.