When you have put a lot of time and effort into a bid, it can be difficult to accept an unsuccessful outcome. Sometimes another bidder will have put together a cheaper or better bid and there is nothing you can do about it. But on other occasions you may have grounds for challenging the decision of the public body.
How can you best prepare for a procurement challenge? Here are our top 10 tips.
Before you submit your bid:
1. Review the invitation to tender carefully. Does it contain any requirements which might breach one of the procurement principles of equal treatment, non-discrimination and transparency? If so, you need to raise them now. It is not an option to wait and see if you win and only raise your complaints about the invitation to tender in the event you are unsuccessful.
2. Keep a note of any correspondence you have with the public body, including any requests for clarification you submit and any verbal discussions. The timing of such discussions could be key to whether your claim is brought in time.
3. Monitor the running of the tender carefully. Make sure you read and understand the response to any requests for clarification submitted by other bidders.
4. Ensure that you submit your bid, including all accompanying documents, on time and in the manner required by the invitation to tender. Your bid may not be considered and/or your scores may be penalised if you forget to attach a key document or upload the wrong version.
Sometimes another bidder will have put together a cheaper or better bid and there is nothing you can do about it. But on other occasions you may have grounds for challenging the decision of the public body.
Once you receive the contract award notice:
5. Share the notice with your bid team and obtain their urgent input on the decision. The people who drafted the individual sections of the bid are usually best placed to know if they have been marked fairly. Consider whether the evaluators have properly understood your bid and if the marks you have received are consistent with the evaluators’ comments. Has another bidder been given higher marks than you without good reason?
6. Check the maths. A surprising number of the challenges we see are based on simple numerical errors in the scoring. Other common issues include weightings being incorrectly applied, too many or too few marks being awarded and marks being awarded on the basis of subcriteria not made available to the bidders. It is more difficult, although not impossible, to bring a challenge on the basis that you simply believe that the score awarded is too low as evaluators are allowed a margin of appreciation and the courts will only interfere where there has been an obvious mistake.
7. Ask the public body for further detail and a breakdown of the scoring, if the information in the contract award notice is not sufficiently detailed for you to determine whether you have been marked fairly.
8. Keep on top of dates and deadlines. There is a very limited period of time in which to challenge the award of a contract. The standstill period, during which the public authority cannot award the contract, runs for just ten days. The absolute limitation period for bringing a claim expires after 30 days.
9. If you need more time, consider asking the public body to extend the standstill period. But do remember the extension of time cannot take you beyond 30 days from the contract award notice.
10. Consult your lawyers at an early stage if you want to bring a challenge. Although quick turnarounds can be achieved, it is not ideal to leave this until the very end of the standstill period.
Our experienced Public Procurement lawyers offer legal support and advice to businesses and public bodies across a number of sectors.
About this article
-
Subject10 Tips for Challenging the Result of a Public Tender
-
Author
-
Expertise
-
Published11 May 2017
Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.
About this article
-
Subject10 Tips for Challenging the Result of a Public Tender
-
Author
-
ExpertisePublic Procurement
-
Published11 May 2017