Search

How can we help?

Icon

Adjudication decision cannot be used to resist prior adjudication

In M Davenport v Greer, one of the first cases to follow the court of Appeal’s decision in S&T v Grove, the TCC held that an employer could not use a “true value” adjudication decision as a defence or set off to enforcement proceedings for an earlier decision in favour of the contractor.

Background

M Davenport Builders (MDB) carried out building work for the Greers under a contract which contained no provisions for payment and so the payment terms of the Scheme for Construction Contracts were implied into the contract.  When MDB issued a final account for £106,160.84, the Greers did not pay but failed to issue a payment or pay less notice.

MDB commenced an adjudication for the unpaid sum (plus interest) and was successful.  The Greers did not pay the sum awarded to MDB and instead commenced a second adjudication (before a different adjudicator) as to the true value of the works.  The adjudicator decided in favour of the Greers that no money was payable to MDB.

MDB brought enforcement proceedings to the TCC in respect of the unpaid award in the first adjudication decision.  The Greers defended the proceedings on the basis that the decision in the second adjudication could be used as a set-off or counterclaim.

Decision

Stuart-Smith J held that the Greers could not rely on the decision in the second adjudication as a ground to avoid paying the sum awarded in the first adjudication.  He followed the reasoning of S&T v Grove  that the first “smash and grab” adjudication created an immediate obligation to make payment, which had to be done before commencing a second adjudication as to the value, and on that basis held that because the Greers had failed to discharge that obligation, they could not rely on the result of the second adjudication to resist enforcement of the first decision.

Although S&T v Grove related to interim applications, Stuart-Smith J found no significant reason to justify a difference in approach for a final application, on the basis that deprivation of cashflow could have serious effects for a contractor whether it occurred during or at the end of the works.

However, although the decision in S&T v Grove was clear that payment was required before a true value adjudication could be commenced, Stuart-Smith J did not determine any issue relating to the jurisdiction of the second adjudicator, on the basis that the question of jurisdiction for the second adjudication did not need to be determined given that he had held that the Greers could not rely on the decision in that adjudication.  Instead, citing Harding v Paice [2015] EWCA Civ 1231, he noted that in that case a party discharging its payment obligation from a first adjudication was not a prerequisite to that party commencing a second adjudication.

This element of the decision does not entirely follow S&T v Grove, which held that the payment obligation must be discharged before the second adjudication can be commenced.  Despite finding that there was no distinction between the interim and final payment contexts, by not applying Grove to the issue of jurisdiction of the second adjudication, Stuart-Smith J implicitly creates a distinction i.e. that Grove fetters the right to adjudicate in the case of interim payments, but not for final payments.

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Practical implications

This is the first reported case to apply last year’s Court of Appeal decision in S&T v Grove. Critically, it confirms that S&T v Grove applies to true value adjudications after an initial “smash and grab” adjudication in the context of both interim and final payment applications.

Whilst the principle makes sense, however, questions remain over whether it is commercially practical, particularly in light of the decision that the second adjudicator will not necessarily lack jurisdiction (which means that the second adjudication may be able to proceed, and be relied upon and enforced, but only once the payment awarded in the first adjudication has been made).  It is not obvious why an employer should be obliged to pay the sum from the first adjudication when they already have a further decision that that sum is not the true value and so is not due to be paid.  All that will happen in those circumstances is that the employer has to pay the sum awarded in the first adjudication and then commence enforcement proceedings to recover it on the basis of the second decision, instead of dealing with both decisions by means of set-off.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

Pub
  • 09 July 2026
  • Litigation and dispute resolution

The Arbitration Act 2025 – Factsheet

This factsheet outlines the major reforms and key developments introduced by the Arbitration Act 2025, including updates on summary disposal, jurisdictional challenges, emergency arbitrators, arbitrator disclosure duties, and governing law in arbitration proceedings.

art
  • 09 July 2026
  • Immigration

Right to Work Checks are changing from 1 October 2026: Is your business ready?

The Home Office’s new rules, effective 1 October 2026, will overhaul right to work checks and raise the risk of civil penalties for UK businesses.

art
  • 08 July 2026
  • Privacy and Data Protection

ICO prosecutes employee under the Data Protection Act for forwarding client data to his personal email address

The issue of employees taking confidential business information or personal data when moving to a new employer remains a significant concern for businesses.

Pub
  • 07 July 2026
  • Litigation and dispute resolution

Accelerating arbitration: Expedited procedures and key changes in the new ICC Rules – Episode 2

In episode 2, Jack Hobbs (Clarkslegal) and Christopher Howitt (Three Stone) explore how the latest expedited and highly expedited procedures under the ICC Arbitration Rules 2026 are transforming the landscape of dispute resolution.

art
  • 07 July 2026
  • Employment

6 month unfair dismissal rights: What employers need to know

Under the new Employment Rights Act 2025 the minimum period of service required to qualify to bring a statutory claim for unfair dismissal has been reduced from 2 full years to 6 months from 1 January 2027 onwards.  

art
  • 02 July 2026
  • Litigation and dispute resolution

Litigation and Artificial Intelligence: Where are we now?

In the recent case of Cork and another v Smith, the High Court publicly admonished a law firm and two of its solicitors after they had produced and submitted two AI-generated letters to the court containing misleading and false information in relation to a block transfer application made under Rule 12.37 of the Insolvency (England and Wales) Rules 2016.