How do I prove my final account claim?

Many construction disputes relate to the calculation of the final account. Sometimes there may be an interesting point of law or expert evidence at stake.  More often than not, the dispute will boil down to proving what work was done and / or what was the agreed price for the work.

These issues came into play in the recent case of Premier Engineering (Lincoln) Limited v MW High Tech Project UK Limited. The underlying project was very large (£150m) but Premier started work on a very small subcontract. When MW fell out with another subcontractor Premier agreed to supply additional labour to help MW the project back on track.  The work was carried out on an ad hoc basis – MW told Premier each week what work was required, Premier did the work and invoiced according to its timesheets. Come the end of the project, the parties were unable to agree Premier’s final account.  Premier claimed an additional £1.3m, whereas MW said that it had already overpaid.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The labour charges represented by far the largest part of the claim.  Premier’s claim relied on its timesheets that had been signed each week by an authorised MW representative.  MW sought to distance itself from the timesheets for two reasons. Firstly, it said that it signed the timesheets without carefully checking them ‘to keep the peace’.  Secondly, the turnstile records at site suggested that the hours worked were lower than claimed.  The Judge rejected both arguments.

Signed timesheets are primary evidence that work has been done. It was MW’s own fault if it had not adequately resourced the job to check the timesheets before signing them off.  This was the best opportunity for MW to raise any concerns about the sums claimed. In any event, MW had challenged the timesheets from time to time.

Turnstile data could have been relevant evidence.However, in this case Premier had raised concerns about the turnstiles – sometimes they were not working and on other occasions Premier’s operatives were working outside the area covered by the turnstiles. The Judge concluded that the parties had agreed that the turnstile data would not be taken into account. They agreed instead to use a biometric clock but this was not installed on site until a later date.

The dispute fell into two main categories – labour and materials – which the court unravelled over the course of an 80 page judgment.

The materials claim threw up a different challenge.  About £100k turned on the claim but it covered very many individual invoices, some of which were low value.  It would not have been realistic for the court to consider every invoice.  Instead it applied a ‘materiality threshold’ to exclude the lowest value invoices. It examined a representative sample of the remainder and used the conclusions on these to determine what was due under the entire batch of invoices.

The case is good illustration of how the court will approach such a claim and the challenges of determining a final account that it for a large sum but made up of very small items.  It also emphasises the importance the claiming party keeping contemporaneous records and the paying party raising objections at the time.

Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.

Author profile

About this article

Read, listen and watch our latest insights

art
  • 23 June 2026
  • Employment

Pride month and employment law: Ensuring compliance with LGBTQ+ protections

With each Pride month, companies unveil rainbow logos and send office wide emails of solidarity. These gestures are valuable, giving visible demonstrations of support, but only really make a difference if those companies are able to truly say that their policies and practices are inclusive and legally compliant.

art
  • 22 June 2026
  • Commercial Real Estate

Do you need an EPC for lease renewals? Key insights for commercial property owners

When is an EPC required for leases? The non-domestic EPC guidance makes it clear that an EPC is not required on renewal. The Ministry for Housing, Communities and Local Government’s (MHCLG’s) “A guide to energy performance certificates for the construction, sale and let of non-dwellings: Improving the energy efficiency of our buildings”

Pub
  • 18 June 2026
  • Employment

Employment Rights Act 2025: Key Changes for Employers

Join Katie Glendinning and Lucy White for an on demand webinar as they break down the key changes introduced by the Employment Rights Act 2025, offering clear insights into what these reforms mean in practice for employers and HR professionals.

art
  • 18 June 2026
  • Corporate and M&A

Business sales and NDAs: Creating a safe space to open up your business

You have accepted an offer to sell your business, but taking an agreement in principle through to completion may involve the need to divulge your company’s private information – perhaps deep secrets which have given your business its competitive edge.  

art
  • 16 June 2026
  • Employment

Shaping the Future of Work: Insights from the 114th ILO International Labour Conference

Having recently returned from the 114th Session of the International Labour Conference in Geneva, I have been reflecting on the work of the International Labour Organisation (ILO) and the important role it plays in global standard setting, as well as promoting social and economic inclusivity.

art
  • 11 June 2026
  • Immigration

MAC report reveals who stays in the UK on the Skilled Worker Route – Key insights for employers

Key insights from the MAC report: Who stays in the UK on the Skilled Worker route? Essential findings and takeaways for employers.