Court of Appeal guidance on Practical Completion
- 11 April 2019
- Litigation and dispute resolution
The facts
The second and third respondents, Pickstock (the contractor) and PNSL (the landlord) entered into a building contract based on JCT Design & Build 2011 in May 2016 to design and build two blocks of student accommodation in Plymouth. Mears, a company providing managed student accommodation, entered into an agreement for lease with PNSL to take a long lease of the property following completion.
Clause 6.2.1 of the agreement for lease prevented PNSL from making any variations to the building works which materially affected the size of the rooms. A reduction in size of more than 3% was deemed to be material. The agreement for lease defined practical completion by reference to the building contract as “A certificate issued by the Employer’s Agent to the effect that practical completion of the Landlord’s Works has been achieved in accordance with the Building Contract.” There was no definition of Practical Completion in the building contract.
In August 2018, Mears sought (and was granted) an injunction preventing Costplan, the Employer’s Agent, from issuing the certificate of practical completion.
Mears argued that any failure to meet the 3% tolerance was a material and substantial breach of the Agreement for Lease which (i) entitled it to terminate and (ii) prevented Costplan, from certifying practical completion.
At first instance, the judge rejected Mears’ arguments and held that a material variation for the purposes of clause 6.2.1 did not automatically mean a material and substantial breach and that whether practical completion could be certified depended on the facts. Mears appealed the decision. The Court of Appeal upheld the decision of the TCC and summarised the law on the meaning of practical completion.
Meaning of Practical Completion
The Court of Appeal summarised the law as follows:
The court said in the absence of any contractual definition or control, whether practical completion has been achieved (i.e. whether the works are free from patent defects save any that are “trifling”) is in the first instance a matter for the certifier. The court also emphasised that the fact that the property was habitable as student accommodation did not automatically mean that the property was practically complete.
The court said in the absence of any contractual definition or control, whether practical completion has been achieved is in the first instance a matter for the certifier.
Comment
As the court itself recognised there are no hard and fast rules and whilst this is a helpful summary of the law, whether or not practical completion has been achieved will continue to be assessed on a case by case basis and as such be a potential area for disputes.
Keep up to date with the latest tips, analysis and upcoming events by our legal experts, direct to your inbox.
Disclaimer
This information is for guidance purposes only and should not be regarded as a substitute for taking legal advice. Please refer to the full General Notices on our website.